Machinery Installation Prep

With the Tech Pro Green facility having been newly renovated, the next step in our was to install the ancillary machinery required so our new machinery can produce our green alternatives to single use plastic through manufacturing industrial and home compostable bioplastics. This included the installation of electrical switchgear and cables along with air compressor and connection lines prior to being tested and certified by the relevant government authority prior to use.

Fac32.jpg

Air filters, water drain traps and isolation valves with air gun for cleaning

Air drier being unpacked and checked before installation

Fac25.jpg
Fac26.jpg

Air compressor, unpacked and checked before installation

Air line water drain traps and isolation valves for 3 machines and air gun for cleaning

Fac30.jpg
Fac29.jpg

Air Compressor and air drier fully installed awaiting regulatory testing and certification before being ready for use